A total of 3.100 m, ø65 cm bored pile and a total of 12.500 m, ø80 cm jet grout column have been constructed within the scope of soil improvement of Adapazari Tsusho Factory Extension Project. Additionally, in order to eliminate the settlement problems in the present building, a total of 27.770 m ø80cm jet grout column and a total of 3.000 m ø35cm mini deep soil mixing column have been constructed.
Services given:
Applications: