Within the scope of soil investigation of Siemens Gebze Factory Production Facility Phases 2-3 and MS Production Facility Projects, 48 soil boring (920 m), geophysical works and pressuremeter and ve plate loading tests have been carried out. Following the soil investigation, based on a geotechnical design soil improvement and shoring have been succesfully implemented when necessary. Within the scope of soil improvement, a total of 17.200 m ø60 cm and ø80 cm jet grout columns have been constructed. Furthermore, within the scope of shoring projects, sloping and soil nail mini pile works have been implemented.
Services given:
Applications: